The Ohio Dept. of Transportation Grant Project “Sharon Rd, County Route 235”, between Morse Ave. and the RR track, and includes resurfacing, storm drains and curbing, has been postponed until late June/early July and will now follow the below listed schedule;
June 28th; Recovery and Investment Act signs installed at project site.
July 5th; Drainage work commences
July 12th; Curb work commences
July 19th; Mill road and blacktop
July 26th; Paint stripes and finish
Beginning July 5th, the road will be subject to lane closures between 8:30am to 4:30pm weekdays. Thank you for your patience.